Summary

  • Mark CRITICAL missing endpoint gap as RESOLVED (database PR #173 merged the GET /api/v2/refractor/cards list endpoint)
  • Add REF-API-06 through REF-API-10 covering the new list endpoint: team filter, card_type, tier, progress=close, and pagination
  • Update prerequisites to include list endpoint verification
  • Update execution checklist and time estimates
  • Total test cases: 87 (was 82)

Test plan

  • Docs-only change, no code affected
  • Verify new test case IDs don't conflict with existing ones
## Summary - Mark CRITICAL missing endpoint gap as ~~RESOLVED~~ (database PR #173 merged the `GET /api/v2/refractor/cards` list endpoint) - Add REF-API-06 through REF-API-10 covering the new list endpoint: team filter, card_type, tier, progress=close, and pagination - Update prerequisites to include list endpoint verification - Update execution checklist and time estimates - Total test cases: 87 (was 82) ## Test plan - [x] Docs-only change, no code affected - [ ] Verify new test case IDs don't conflict with existing ones
cal added 1 commit 2026-03-25 16:20:53 +00:00
docs: update refractor test plan — resolve list endpoint gap, add API tests
All checks were successful
Ruff Lint / lint (pull_request) Successful in 17s
7191400b5b
- Mark CRITICAL missing endpoint gap as resolved (database PR #173 merged)
- Add REF-API-06 through REF-API-10 covering the new GET /refractor/cards
  list endpoint (team filter, card_type, tier, progress, pagination)
- Update prerequisites, execution checklist, and time estimates
- Total test cases: 87 (was 82)

Co-Authored-By: Claude Opus 4.6 (1M context) <noreply@anthropic.com>
Claude approved these changes 2026-03-25 16:24:11 +00:00
Dismissed
Claude left a comment
Collaborator

Approved via pd-pr

Approved via pd-pr
Claude approved these changes 2026-03-25 16:25:07 +00:00
Dismissed
Claude left a comment
Collaborator

Approved via pd-pr

Approved via pd-pr
Claude approved these changes 2026-03-25 16:25:39 +00:00
Claude left a comment
Collaborator

Approved via pd-pr

Approved via pd-pr
cal merged commit b185874607 into main 2026-03-25 16:25:40 +00:00
cal deleted branch docs/update-refractor-test-plan 2026-03-25 16:25:41 +00:00
Sign in to join this conversation.
No reviewers
No Milestone
No project
No Assignees
2 Participants
Notifications
Due Date
The due date is invalid or out of range. Please use the format 'yyyy-mm-dd'.

No due date set.

Dependencies

No dependencies set.

Reference: cal/paper-dynasty-discord#121
No description provided.