major-domo-database/PRODUCTION_MIGRATION_CHECKLIST.md
Cal Corum 79a559088a CLAUDE: Phase 1 PostgreSQL migration fixes complete
- Fixed 4 critical schema issues blocking migration
- Resolved integer overflow by converting Discord IDs to strings
- Fixed VARCHAR length limits for Google Photos URLs
- Made injury_count field nullable for NULL values
- Successfully migrating 7/30 tables (5,432+ records)

Issues resolved:
- CONSTRAINT-CURRENT-INJURY_COUNT-001: Made nullable
- DATA_QUALITY-PLAYER-NAME-001: Increased VARCHAR limits to 1000
- MIGRATION_LOGIC-TEAM-INTEGER-001: Discord IDs now strings
- MIGRATION_LOGIC-DRAFTDATA-INTEGER-001: Channel IDs now strings

New issues discovered for Phase 2:
- CONSTRAINT-CURRENT-BSTATCOUNT-001: NULL stats count
- CONSTRAINT-TEAM-AUTO_DRAFT-001: NULL auto draft flag

🤖 Generated with [Claude Code](https://claude.ai/code)

Co-Authored-By: Claude <noreply@anthropic.com>
2025-08-18 18:09:45 -05:00

8.0 KiB

Production Migration Checklist

🎯 Pre-Migration Requirements

ALL items must be completed before production migration

Testing Validation

  • 100% sandbox migration success - All tables migrated without errors
  • Data integrity verified - Record counts match exactly between SQLite/PostgreSQL
  • Performance acceptable - Migration completes within maintenance window
  • Rollback tested - Confirmed ability to revert to SQLite if needed
  • Team sign-off - Technical and business stakeholders approve migration

Infrastructure Readiness

  • PostgreSQL server provisioned - Production hardware/cloud resources ready
  • Backup systems configured - Automated backups for PostgreSQL
  • Monitoring enabled - Database performance and health monitoring
  • Security hardened - Access controls, encryption, firewall rules
  • Network connectivity - Application servers can reach PostgreSQL

Application Readiness

  • Environment variables updated - DATABASE_TYPE=postgresql in production
  • Connection pooling configured - Appropriate pool sizes for PostgreSQL
  • Dependencies updated - psycopg2-binary installed in production
  • Query compatibility verified - All LIKE queries use ILIKE where needed
  • Error handling updated - PostgreSQL-specific error codes handled

🚀 Migration Day Execution Plan

Phase 1: Pre-Migration (T-2 hours)

  • Notify stakeholders - Send migration start notification
  • Application maintenance mode - Put application in read-only mode
  • Final SQLite backup - Create point-in-time backup
  • PostgreSQL preparation - Ensure target database is ready
  • Team assembly - All migration team members available

Phase 2: Data Migration (T-0 to T+X)

  • Start migration script - Begin migrate_to_postgres.py
  • Monitor progress - Track migration status and performance
  • Handle issues - Apply pre-tested fixes for any problems
  • Validate data integrity - Run validate_migration.py
  • Performance verification - Test key application queries

Phase 3: Application Cutover (T+X to T+Y)

  • Update environment variables - Switch to PostgreSQL
  • Restart application services - Deploy with PostgreSQL configuration
  • Connection testing - Verify application connects successfully
  • Functional testing - Test critical user workflows
  • Performance monitoring - Watch for performance issues

Phase 4: Go-Live Verification (T+Y to T+Z)

  • Remove maintenance mode - Enable full application access
  • User acceptance testing - Key users verify functionality
  • Performance monitoring - Monitor system under user load
  • Data consistency checks - Ongoing validation of data integrity
  • Issue escalation - Address any problems immediately

🔄 Rollback Procedures

Immediate Rollback Triggers

  • Data corruption detected - Any indication of data loss or corruption
  • Performance degradation > 5x - Unacceptable application performance
  • Critical functionality broken - Core features not working
  • Security concerns - Any security-related issues discovered
  • Team consensus - Migration team agrees rollback is necessary

Rollback Execution (Emergency)

# 1. Immediate application switch
export DATABASE_TYPE=sqlite
systemctl restart application

# 2. Verify SQLite connectivity
python test_sqlite_connection.py

# 3. Notify stakeholders
send_rollback_notification.sh

# 4. Document issues
echo "Rollback executed at $(date): $(reason)" >> rollback_log.md

Post-Rollback Actions

  • Root cause analysis - Identify what went wrong
  • Issue documentation - Update migration issues tracker
  • Fix development - Address problems in sandbox
  • Retest thoroughly - Validate fixes before retry
  • Stakeholder communication - Explain rollback and next steps

📊 Success Criteria

Quantitative Metrics

  • Migration time: < 4 hours total
  • Data accuracy: 100% record count match
  • Query performance: < 2x SQLite response times
  • Downtime: < 1 hour application unavailability
  • Error rate: 0 critical errors during migration

Qualitative Indicators

  • User experience: No degradation in functionality
  • System stability: No crashes or instability
  • Team confidence: High confidence in system reliability
  • Monitoring clean: No critical alerts or warnings
  • Documentation current: All procedures documented

🔧 Emergency Contacts

Technical Team

  • Database Admin: [contact] - PostgreSQL expertise
  • Application Lead: [contact] - Application configuration
  • DevOps Engineer: [contact] - Infrastructure support
  • QA Lead: [contact] - Testing and validation

Business Team

  • Product Owner: [contact] - Business impact decisions
  • Operations Manager: [contact] - User communication
  • Security Officer: [contact] - Security concerns
  • Compliance Lead: [contact] - Regulatory requirements

📋 Pre-Flight Checklist (Final 24 Hours)

Technical Verification

  • Sandbox migration - Final successful test run completed
  • Production database - PostgreSQL server health verified
  • Backup systems - All backup procedures tested
  • Monitoring dashboards - All alerts and monitors active
  • Rollback plan - Tested and verified within 2 hours

Operational Readiness

  • Team availability - All key personnel confirmed available
  • Communication plan - Stakeholder notifications prepared
  • Change control - All approvals and documentation complete
  • Risk assessment - Mitigation strategies for known risks
  • Go/No-Go decision - Final stakeholder approval received

Documentation Current

  • Migration procedures - Step-by-step instructions updated
  • Troubleshooting guides - Known issues and solutions documented
  • Contact information - All emergency contacts verified
  • Rollback procedures - Clear instructions for reverting changes
  • Post-migration tasks - Cleanup and optimization steps defined

📈 Post-Migration Activities

Immediate (24 hours)

  • Performance monitoring - Watch system metrics closely
  • User feedback collection - Gather user experience reports
  • Data validation - Ongoing verification of data integrity
  • Issue tracking - Document any problems discovered
  • Team debrief - Capture lessons learned

Short-term (1 week)

  • Performance optimization - Tune PostgreSQL configuration
  • Index optimization - Create additional indexes if needed
  • Monitoring refinement - Adjust alert thresholds
  • Documentation updates - Update operational procedures
  • Training completion - Ensure team is trained on PostgreSQL

Long-term (1 month)

  • SQLite decommission - Remove old SQLite infrastructure
  • Backup verification - Validate PostgreSQL backup/restore
  • Performance baseline - Establish new performance standards
  • Security audit - Complete security review of new system
  • Success metrics - Measure and report migration success

🎯 Final Authorization

Sign-off Required

  • Database Administrator: _________________ Date: _________
  • Application Lead: _________________ Date: _________
  • DevOps Engineer: _________________ Date: _________
  • QA Lead: _________________ Date: _________
  • Product Owner: _________________ Date: _________
  • Security Officer: _________________ Date: _________

Migration Approval

Authorized to proceed with production migration: YES / NO

Authorized by: _________________ Date: _________ Time: _________

Migration window: Start: _________ End: _________

Rollback deadline: _________


This checklist ensures systematic, safe migration to production with clear success criteria and rollback procedures.